A construction crew must build a road in 10 months or they will be penalized $500,000. It took 10 workers 6 months to build half of the road. How many additional workers must be added to finish the road in the remaining 4 months?

Calculate unit rate per one worker:
10 workers * 6 months = 60 months for one worker

Calculate workers needed:
60 months / 4 months = 15 workers

Calculate additional workers needed:
Additional workers needed = New workers needed - Original workers needed
Additional workers needed = 15 - 10
Additional workers needed = 5 additional workers
 